Brecon Town Centre - Introduction & Overview
Working with Brecon, for Brecon
Welcome to Brecon Town Centre
Everything you need to know about the Brecon Town Centre Improvements — and how we will work together to keep your business, your street, and your community thriving throughout.
Programme Start: March 2026
About the Project
SEER Construction has been appointed by Powys County Council to deliver the Brecon Town Centre Improvements programme.
As a proudly local Welsh company — with directors who grew up in this community — this project matters to us. We are invested in Brecon’s future because it is our future too.
This pack introduces our team, explains how we will work with you, and ensures you always know who to contact.
Your SEER Construction Team
Meet the People on Your Doorstep
Tabby Tunnicliffe
Community Liaison Manager
- Your first point of contact
- Regular visits to keep you informed
- Ensures concerns are addressed quickly
📞 07496 267091 (Call or WhatsApp)
✉️ tabby@seerconstruction.co.uk
Shane Palmer
Site Manager
- Oversees day-to-day site operations
- Ensures safe and efficient delivery
- Minimises disruption wherever possible
✉️ shane@seerconstruction.co.uk
Our Commitment to Brecon
What We Aim to Deliver
- Advance Notice, Always
You’ll always be informed before disruptive works begin. - Access Stays Open
Businesses remain accessible to customers, deliveries, and pedestrians. - Works Planned Around You
We minimise disruption wherever possible. - Fast Response to Concerns
Same-day acknowledgement and quick resolution. - Clear Signage for Customers
“We Are Open” signage and directional guidance provided. - Regular Updates
Weekly updates via email, WhatsApp, in-person visits, and social media.
Staying Connected
How We’ll Communicate
- In-Person Visits
Weekly visits to every business and resident. - WhatsApp Broadcast
Updates twice weekly (Monday & Friday). - Weekly Email Newsletter
Every Friday with progress updates and upcoming works. - Phone & WhatsApp Access
Available Monday–Friday, 7:30am–5:30pm (responses within 2 hours). - Social Media Updates
Weekly videos and milestone updates. - Phase Notice Letters
Issued at least 5 working days before each phase.
How We Can Help
SEER Can Assist With:
- Noise, dust, or vibration
- Access to premises or deliveries
- Scheduling of works
- Signage and “We Are Open” materials
- Site safety concerns
- Working hours adjustments
- Damage caused by works
- General project questions
Council Matters
Tabby will direct you to the right contact for:
- Planning or development queries
- Road closures unrelated to works
- Council services (bins, lighting, cleaning)
- Business rates or grants
Raising a Concern
- Contact Tabby
Call, WhatsApp, or speak in person - Same-Day Acknowledgement
Your concern is always confirmed the same day - Action Within 24 Hours
For SEER-related issues - Follow-Up Confirmation
Nothing is left unresolved
Programme of Works
Phases 1–5
Phase 1 – St Marys Street (New Footpath)
- New footpath construction
- Temporary parking removal
- Work from both ends to speed progress
Phase 2 – New Road (Church to Monument)
- New road formation
- High Street access maintained
Phase 3 – Resurfacing (St Marys Street)
- Road closure (approx. 3–5 days)
- Traffic diverted via High Street
Phase 4 – High Street Connection
- Integration with new road layout
- Traffic diverted via Tredegar Street & Lion Street
- Estimated closure: 2–3 weeks (combined phases)
Phase 5 – Monument Area Works
- Pedestrian improvements
- Temporary traffic stops during key works
Phases 6–12
Phase 6 – Bus Stop Platform & Surfacing
- Road closure required
- Runs alongside other phases
Phase 7 – Lion Street Works
- New kerb and resurfacing
- Temporary closure with local access maintained
Phase 8 – Wider Area Works
- Minimal disruption
- Pedestrian access maintained
Phase 9 – Glamorgan Street Access Closure
- Temporary closure for drainage and resurfacing
Phase 10 – Paving Works
- Museum side and Dan y Gaer entrance
- Temporary road closure
Phase 11 – Bus Stop Closure
- Temporary closure
- Bulwark stop remains open
Phase 12 – Final Resurfacing
- Covers The Watton, High Street, and Lion Street
- Traffic lights used for flow management
Visual Reference
- Plan 1: St Marys Street, High Street, Monument Area (Phases 1–7)
- Plan 2: Glamorgan Street, Dan y Gaer Road, The Watton (Phases 8–11)
Final Note
Thank you for your patience and support.
We are proud to deliver this project in Brecon and are committed to doing it right — for you, for the town, and for the community.
Brecon is open. We’ll make sure of it.
— The SEER Construction Team